Keeping the business case justified
How the business case is reviewed and updated through the project, and what happens when the numbers change.
Scene 1
Keeping the business case justified
How the business case is reviewed and updated through the project, and what happens when the numbers change.
Caption 1 of 3
Describe when the business case is reviewed
Read all scene text
- Describe when the business case is reviewed
- Explain how changes and risks affect the business case
- Recognise when the project board should consider closing a project early
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Describe when the business case is reviewed
- Explain how changes and risks affect the business case
- Recognise when the project board should consider closing a project early
It's time to see the business case working as a living document.
Let's say the damp in Stage 2 pushes the Stage 2 forecast to £45,000, and the coffee chain's opening means forecast York sales drop to £3,200 a week. Sam is preparing for the end of Stage 2.
Is York still worth doing?
Select the arrow to learn more
1 of 4
Update the numbers
Sam updates the business case: total cost now around £90,000, benefits around £3,200 a week. Payback stretches from two years to nearly three.
When it's reviewed
The business case gets a fresh look at several points:
- At the end of each stage, before the board authorises the next one
- When an exception is raised, because the exception plan may change costs or benefits
- When a significant change is considered, to see if it's worth it
- At closure, to confirm what was delivered and what benefits are still expected
Changes, risks and the case
Every big decision on the project has a business case angle. Priya's bigger oven costs £3,000. Is it worth it? Only if it brings enough extra benefit, for example by letting York bake its own bread instead of shipping it from Leeds.
Risks matter too. The business case summarises the major risks to the project's justification. If the overall risk picture gets worse, the case may no longer stack up, even if nothing has gone wrong yet.
When to stop
If the business case can no longer be justified, the project board should change the project or stop it. Closing a project early is a valid business decision, not a failure.
Let's say a bigger national chain had opened a bakery right next door instead. Forecast sales might fall so far that York could never pay back. Stopping before Stage 3 and subletting the shop could save tens of thousands of pounds.
Who checks
The project executive is responsible for making sure the business case stays justified. The project manager keeps it updated, and project assurance checks it independently.
At Fern & Flour, Ruth reviews the updated numbers at each stage end before the board meets. A second pair of eyes stops optimism from creeping in.
Key points to remember
- The business case is reviewed at each stage end, at exceptions, at major changes and at closure.
- Changes and risks are judged by their effect on the business case.
- If the case can't be justified, change the project or close it early.
- The executive is responsible; project assurance checks independently.
Knowledge check
Select all that apply
Practices
Select two points at which the business case is typically reviewed.