Tailor to suit the project

How to adapt PRINCE2 so it fits the project, what can and can't be changed, and where tailoring decisions are recorded.

Sign in to track progress
Guided lesson
~0:22Scene 1 of 7

Scene 1

Tailor to suit the project

How to adapt PRINCE2 so it fits the project, what can and can't be changed, and where tailoring decisions are recorded.

Caption 1 of 3

Explain why PRINCE2 must be tailored

0:00 / 0:22
Read all scene text
  1. Explain why PRINCE2 must be tailored
  2. Identify what can be tailored and what can't
  3. Describe where tailoring decisions are recorded

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Explain why PRINCE2 must be tailored
  • Identify what can be tailored and what can't
  • Describe where tailoring decisions are recorded

It's time for the principle that holds all the others together.

Let's say Sam's last job was a £2 million office move, with 40-page plan templates and a board that met every week. Sam arrives at Fern & Flour with exactly the same templates.

Should Sam use them as they are?

Select the arrow to learn more

1 of 4

Too heavy

Forty-page documents for an £85,000 project would take more time to write than they'd save. Nobody would read them.

What can be tailored

Almost every part of the method can be adapted to fit:

  • Processes: small projects can combine some of them
  • Practices: risk management can be a simple spreadsheet rather than specialist software
  • Roles: one person can hold more than one role
  • Management products: reports can be emails, and some documents can be merged
  • Terms: if your business calls stages "phases", you can use that word

What can't be tailored

The principles. All seven apply to every PRINCE2 project. Tailoring changes how they're applied, never whether they're applied.

Tailoring also isn't an excuse to skip things. Dropping the business case because it's "too much paperwork" isn't tailoring. Writing it as a one-page summary is.

What drives tailoring

Tailoring decisions come from the project context you met in Module 1. The main things to weigh up are:

  • Scale and complexity: York is small and simple, so the method can be light
  • Risk: a riskier project needs tighter control
  • People: an experienced team needs less detailed direction
  • The organisation: its standards, culture and existing ways of working
  • The delivery approach: the pre-order app will be built iteratively, so planning and reporting will look different

Writing it down

Tailoring decisions are recorded in the project initiation documentation, the document that sets out how the project will be run. That way, everyone knows how the method is being applied, and the decisions can be reviewed at each stage boundary if things change.

Key points to remember

  • PRINCE2 must be adapted to fit each project's context.
  • Processes, practices, roles, management products and terms can all be tailored.
  • The seven principles always apply and can't be tailored away.
  • Tailoring decisions are recorded in the project initiation documentation.
Knowledge checkQuestion 1 of 4

Knowledge check

True or false

Principles

Tailoring can make PRINCE2 more formal for a large, high-risk project.

Tailoring can make PRINCE2 more formal for a large, high-risk project.
Choose one answer to continue.