Communication
How to get the right message to the right people at the right time, and why listening matters as much as talking.
Scene 1
Communication
How to get the right message to the right people at the right time, and why listening matters as much as talking.
Caption 1 of 3
Explain why communication must be planned
Read all scene text
- Explain why communication must be planned
- Choose suitable channels and timing for different audiences
- Describe the purpose of the communication management approach
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Explain why communication must be planned
- Choose suitable channels and timing for different audiences
- Describe the purpose of the communication management approach
It's time to look at communication, the thread that ties every stakeholder to the project.
Let's say a rumour starts in the Leeds shop: "They're opening York because Leeds is closing." By Friday, two of your best bakers are looking at job adverts.
What went wrong, and how do you fix it?
Select the arrow to learn more
1 of 4
Silence filled with guesses
The Leeds team had seen builders' invoices and heard whispers about York, but nobody had told them anything directly.
Right message, right channel, right time
Different people need different things. When you plan communication for each audience, think about:
- What they need to know, and what you need from them
- When they need it, for example before a decision, not after
- How: a face-to-face chat, an email, a short message, a notice in the shop window
- Who should deliver it, because people trust some messengers more than others
Formal and informal
Projects need both. Formal communication includes reports to the project board and agreed updates to suppliers. Informal communication is the quick chat on site, the phone call when something looks wrong.
Informal channels are fast and build relationships, but they're easy to forget. Anything that leads to a decision should be confirmed in writing, so there's a clear record.
The communication management approach
PRINCE2 records how a project will communicate in its communication management approach. It's prepared during initiation and sits with the other management approaches.
It describes who the stakeholders are, what information each needs, the methods and frequency of communication, and who's responsible. You'll see it again in the Organising module.
Communication on the app
On the pre-order app, communication has its own rhythm. Ana's team shows a working version to Jo and some regulars at the end of every 2-week cycle. Feedback goes straight into the next cycle.
Short, frequent and visual communication works well for iterative work. Showing people a real screen beats describing it in a long document.
Key points to remember
- Plan what each audience needs, when, how and from whom.
- Communication is two-way: listen and gather feedback, not just inform.
- Confirm in writing anything that leads to a decision.
- The communication management approach records how the project will communicate.
Knowledge check
Choose one answer
People
A rumour is spreading among Leeds staff. What's the best response?
Sign in to save your result. Knowledge checks can be retried any time.