Controlling a stage
How the project manager runs each stage day to day: assigning work, monitoring progress and dealing with issues.
Scene 1
Controlling a stage
How the project manager runs each stage day to day: assigning work, monitoring progress and dealing with issues.
Caption 1 of 3
Describe the purpose of controlling a stage
Read all scene text
- Describe the purpose of controlling a stage
- Name the main activities in controlling a stage
- Explain when the project manager escalates
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Describe the purpose of controlling a stage
- Name the main activities in controlling a stage
- Explain when the project manager escalates
It's time to follow Sam through a typical week in Stage 2.
Let's say it's Monday. The board has authorised Stage 2: the building works, £40,000 and 10 weeks. Now it's Sam's job to make it happen, without running back to the board every day.
What does Sam do this week?
Select the arrow to learn more
1 of 4
Hand out work
Sam authorises a work package for the site foreman: strip-out, damp survey and replastering, with tolerances and a weekly checkpoint report.
Purpose
The purpose of controlling a stage is to assign work, monitor it, deal with issues, report progress to the board and take corrective action so the stage stays within tolerance.
It's used in every delivery stage and in the initiation stage too, if it's long enough to need it.
Main activities
The activities fall into three groups:
- Work packages: authorise a work package, review its status and receive completed work packages
- Monitoring and reporting: review the stage status and report highlights to the board
- Issues: capture and examine issues and risks, take corrective action and escalate issues and risks when needed
Corrective action or escalation
If a problem can be solved within stage tolerance, the project manager takes corrective action: moving work around, using a little of the cost tolerance or adjusting a work package.
If the stage is forecast to go outside tolerance, the project manager escalates to the board with an exception report. That's what Sam did with the damp.
Controlling a stage with iterative delivery
For the app, controlling a stage looks a little different. Each 2-week cycle is like a work package. Sam reviews the team's demo and the backlog at the end of each cycle, rather than detailed task lists.
The principle is the same: assign work, monitor progress, deal with issues and keep the board informed.
Key points to remember
- Controlling a stage is the project manager's day-to-day process.
- It covers work packages, monitoring and reporting, and issues.
- Problems within tolerance get corrective action; forecast breaches are escalated.
- It works with both linear and iterative delivery.
Knowledge check
Choose one answer
Processes
Which report does the project manager send to the board during controlling a stage, at regular intervals?