The risk management approach
How the project decides in advance how risks will be identified, assessed, handled and escalated.
Scene 1
The risk management approach
How the project decides in advance how risks will be identified, assessed, handled and escalated.
Caption 1 of 3
Describe the purpose of the risk management approach
Read all scene text
- Describe the purpose of the risk management approach
- Explain the purpose of the risk register
- Explain the risk budget
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Describe the purpose of the risk management approach
- Explain the purpose of the risk register
- Explain the risk budget
It's time to agree, as a team, how risks will be managed on York.
Let's say Sam rates the damp risk as "high". Dev calls it "medium". Priya hadn't heard about it at all. Everyone's using a different scale, and nobody's sure who should act.
What's missing?
Select the arrow to learn more
1 of 4
A common scale
Sam proposes a simple 1–5 scale for probability and impact, with examples of what each number means for York.
What it covers
The risk management approach is created during initiation and forms part of the PID. It typically covers:
- The procedure for managing risks
- The scales for probability, impact and proximity
- The risk appetite and risk tolerance, and when to escalate
- The roles and responsibilities, including risk owners
- The tools, records and reporting to use
- Use of a risk budget
The risk register
The risk register records every identified risk. It's created during initiation. Each entry usually includes:
- A risk identifier and the author
- The category and description (cause, event, effect)
- Probability, impact and proximity
- The risk response category and planned actions
- The risk owner, risk actionee and current status
The risk budget
A risk budget is money set aside to fund risk responses, such as fallback plans, if needed. York has a £5,000 risk budget.
It's separate from the change budget, which pays for requested changes. Keeping them apart stops the change budget being used up on risks, or the other way round.
Fit the approach to the project
For York, the approach is two pages, a 1–5 scale and a spreadsheet register. A project building a hospital would need formal risk workshops, software and independent risk reviews.
Tailor the approach to the size and risk of the project, but always make sure everyone uses the same procedure and scales.
Key points to remember
- The risk management approach describes how risk will be managed on the project.
- It's created during initiation and is part of the PID.
- The risk register records each risk's description, assessment, response, owner and status.
- The risk budget funds risk responses and is separate from the change budget.
Knowledge check
Choose one answer
Practices
What is the risk budget used for?
Sign in to save your result. Knowledge checks can be retried any time.