Levels of plan
Why PRINCE2 uses project, stage and team plans, who each one is for and when an exception plan replaces one.
Scene 1
Levels of plan
Why PRINCE2 uses project, stage and team plans, who each one is for and when an exception plan replaces one.
Caption 1 of 3
Name the levels of plan in PRINCE2
Read all scene text
- Name the levels of plan in PRINCE2
- Describe who uses each level and who approves it
- Explain the purpose of a plan
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Name the levels of plan in PRINCE2
- Describe who uses each level and who approves it
- Explain the purpose of a plan
It's time to look at how PRINCE2 plans a project at different levels of detail.
Let's say Sam brings one giant plan to the first board meeting. It's 400 lines long and includes "order grout for staff toilet, Tuesday week 7". You can't see whether the shop will open by 1 December.
What does each person need to see?
Select the arrow to learn more
1 of 4
The board
You need the big picture: the stages, the major products, the total cost and the opening date. That's the project plan.
What a plan is for
A plan describes what will be delivered, how, by whom, when and for how much. It's also the baseline the project is measured against.
Without a plan, you can't tell whether the project is ahead or behind, or whether a problem matters. Planning also forces people to think things through before they spend money.
The three levels
Each level has a different owner and audience:
- Project plan: an overview of the whole project, its stages, major products, costs and timeline. Created during initiation and approved by the project board
- Stage plan: the detail for one management stage, created near the end of the previous stage. Approved by the project board
- Team plan: optional detail for a work package, created by the team manager. Agreed with the project manager
Exception plans
When a stage or the project is forecast to go outside tolerance, the board may ask for an exception plan. It replaces the plan it's for and shows how the project will recover.
When the damp pushes Stage 2's forecast to £45,000, Sam prepares a Stage 2 exception plan. The project board approves it. If the whole project were forecast to go outside its tolerances, the exception plan would replace the project plan and the business layer would approve it.
Plans are more than schedules
A PRINCE2 plan isn't just a Gantt chart. It includes the products, the activities, the resources, the costs, the tolerances, the assumptions and the risks.
A one-page plan can be enough for a small project. The York project plan fits on four pages: a timeline, a stage list, a budget table and a list of key assumptions.
Key points to remember
- A plan covers what, how, by whom, when and for how much.
- PRINCE2 has project plans, stage plans and optional team plans.
- Stage plans are produced near the end of the previous stage.
- Exception plans replace a project or stage plan, never a team plan.
Knowledge check
Choose one answer
Practices
Who approves a stage plan?
Sign in to save your result. Knowledge checks can be retried any time.