The issue management procedure
The five steps for handling formal issues, and the records used along the way.
Scene 1
The issue management procedure
The five steps for handling formal issues, and the records used along the way.
Caption 1 of 3
Name the steps in the issue management procedure
Read all scene text
- Name the steps in the issue management procedure
- Describe the purpose of the issue register and issue report
- Describe the options for responding to requests for change and off-specifications
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Name the steps in the issue management procedure
- Describe the purpose of the issue register and issue report
- Describe the options for responding to requests for change and off-specifications
It's time to handle Priya's bigger oven request properly.
Let's say Priya emails Sam: the oven in the plan is fine for now, but a bigger one would let York bake for a new wholesale customer too. It costs £3,000 more.
How should Sam handle it?
Select the arrow to learn more
1 of 4
Capture
Sam logs it in the issue register as a request for change and decides it needs formal handling, because it changes the approved equipment list.
The five steps
The issue management procedure has five steps:
- Capture: record the issue and decide whether to handle it formally or informally
- Assess: understand its effect on the project's objectives and the business case
- Recommend: identify the options and recommend a response
- Decide: the right person decides, whether the project manager, the change authority or the board
- Implement: carry out the decision and update the affected plans and products
Records
Issues use these records:
- Daily log: informal issues the project manager handles directly
- Issue register: every formal issue, with its type, date, status and priority
- Issue report: a fuller description of a formal issue, its effects and the recommendation, when a decision is needed
Responding to a request for change
For a request for change, the decision-maker can:
- Approve it, funding it from the change budget, by cutting scope elsewhere or by asking for more money
- Reject it
- Ask for an exception plan, if the change would take the project outside tolerance
- Request more information before deciding
Responding to an off-specification
For an off-specification, the options are:
- Accept it as it is, without corrective action. This is called a concession
- Reject it and have it fixed, funded from the change budget, through an exception plan or under the supplier's contract
Key points to remember
- The issue procedure is capture, assess, recommend, decide and implement.
- Formal issues go in the issue register; issue reports support decisions.
- Requests for change can be approved, rejected, escalated by exception or deferred for more information.
- Accepting an off-specification without corrective action is a concession.
Knowledge check
Choose one answer
Practices
Which step of the issue procedure comes after assess?
Sign in to save your result. Knowledge checks can be retried any time.