Manage by stages
How breaking a project into management stages gives you control, and why you only commit to one stage at a time.
Scene 1
Manage by stages
How breaking a project into management stages gives you control, and why you only commit to one stage at a time.
Caption 1 of 3
Explain what a management stage is and why it gives control
Read all scene text
- Explain what a management stage is and why it gives control
- Describe the minimum number of management stages
- Explain how detailed and high-level planning work together
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Explain what a management stage is and why it gives control
- Describe the minimum number of management stages
- Explain how detailed and high-level planning work together
It's time to look at how you keep a project under control without committing everything at once.
Let's say you've decided to go ahead with York. Tom, your co-director, asks a simple question: "Are we signing off the whole £85,000 today?"
How much would you commit on day one?
Select the arrow to learn more
1 of 4
Everything at once
You'd be spending money before you know whether the lease is signed, the planning permission is granted or the damp survey is clear. That's a big gamble.
Management stages
A management stage is a section of the project that's approved and managed as a unit. At the end of each one there's a decision point, where the people directing the project decide whether to carry on.
This lets you commit money and people in manageable chunks. If the damp survey comes back bad in Stage 1, you've only spent the cost of Stage 1, not the whole budget.
Plan near things in detail, far things in outline
You can't plan week 12 in detail on day one. Too much will change. So PRINCE2 uses two levels of plan at once:
- A project plan, in outline, for the whole project: the three stages, the main products, the overall budget and opening date
- A stage plan, in detail, for the current stage only: who does what, week by week
How many stages?
Every PRINCE2 project has at least two management stages: an initiation stage, where the project is planned properly, and at least one more stage to deliver the work.
Beyond that, it depends on the project. Shorter stages mean more decision points and more control, but more time spent reviewing. Riskier, more complex projects usually need more stages. York has three.
Stages and the work don't have to line up
Management stages are about decision points, not about types of work. The specialist work doesn't have to fit neatly inside them. The electrician might start in Stage 2 and finish in Stage 3.
On the pre-order app, one management stage might contain several short development cycles. The board still makes its decisions stage by stage, while the team works in its own rhythm inside each stage.
Key points to remember
- A project is planned, monitored and controlled one management stage at a time.
- Each stage ends with a decision point where the project is reviewed before the next stage is approved.
- There are at least two management stages: initiation plus at least one more.
- The project plan is in outline. Each stage plan is in detail.
Knowledge check
Choose one answer
Principles
What is the minimum number of management stages in a PRINCE2 project?
Sign in to save your result. Knowledge checks can be retried any time.