Manage by exception
How agreed tolerances let people get on with the job, and when a problem has to be passed up to the next level.
Scene 1
Manage by exception
How agreed tolerances let people get on with the job, and when a problem has to be passed up to the next level.
Caption 1 of 3
Explain how tolerances support manage by exception
Read all scene text
- Explain how tolerances support manage by exception
- Describe the four levels of authority and who sets which tolerances
- Explain when an issue must be escalated
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Explain how tolerances support manage by exception
- Describe the four levels of authority and who sets which tolerances
- Explain when an issue must be escalated
It's time to look at how much the people in charge really need to know.
Let's say Sam rings you every day. Tuesday: a £40 delivery charge. Wednesday: the shade of the paint. Thursday: whether the builder can start at 8 rather than 7.30.
Is this good management?
Select the arrow to learn more
1 of 4
Too much
You're running the Leeds shop and baking from 4am. You don't need every detail, and Sam can't work if every small decision waits for you.
Tolerances across all seven targets
Tolerances can be set for any of the seven performance targets. For Stage 2 of the York project, they might look like this:
- Time: up to one week late
- Cost: £40,000, plus or minus £3,000
- Scope: the kitchen and counter are must-haves, while the window seat is optional
- Quality: kitchen surfaces must meet food-safety standards, with no tolerance at all
- Risk: any single threat that could cost more than £5,000 must be reported
- Benefits: forecast weekly sales can fall up to 10% below plan before you're told
- Sustainability: at least 85% of building waste recycled
Four levels of authority
Manage by exception works through layers. Each level sets tolerances for the level below and only gets involved when those tolerances are threatened:
- The business layer sets tolerances for the whole project. At Fern & Flour, that's you and Tom as the company's directors.
- The project board directs the project and sets tolerances for each stage. It agrees Stage 2's limits with Sam.
- The project manager runs each stage day to day and sets tolerances for each package of work given to a team. Sam agrees limits with the builder's site foreman.
- The teams do the specialist work within those limits.
Escalate on the forecast, not the damage
An exception is raised as soon as a tolerance is forecast to be exceeded, not after it's happened. When the builder finds damp and the cost forecast for Stage 2 jumps to £45,000, Sam escalates that day. The board then has time to choose: approve the extra cost, cut scope elsewhere or rethink the stage.
If the problem is small enough to stay inside tolerance, Sam deals with it and simply reports it in the next regular update.
Why it works
Managing by exception makes good use of senior people's time. They set the direction and the limits, then step back. The people closest to the work can act quickly, and there's a clear path for escalation when it's needed.
It doesn't mean silence, though. Sam still sends regular progress updates. Manage by exception simply means the board isn't asked to make decisions that sit within someone else's limits.
Key points to remember
- Tolerances are agreed limits around the seven performance targets.
- The business layer sets project tolerances, the project board sets stage tolerances and the project manager sets work package tolerances.
- Escalate as soon as a tolerance is forecast to be exceeded.
- Regular reporting continues. Only decisions outside tolerance are passed up.
Knowledge check
Choose one answer
Principles
Who sets the tolerances for a management stage?
Sign in to save your result. Knowledge checks can be retried any time.