Product-based planning

How PRINCE2 starts every plan with the products, using a product breakdown structure, product descriptions and a product flow diagram.

Sign in to track progress
Guided lesson
~0:26Scene 1 of 7

Scene 1

Product-based planning

How PRINCE2 starts every plan with the products, using a product breakdown structure, product descriptions and a product flow diagram.

Caption 1 of 3

Describe the steps in PRINCE2 planning

0:00 / 0:26
Read all scene text
  1. Describe the steps in PRINCE2 planning
  2. Explain the purpose of the project product description
  3. Describe the product breakdown structure, product descriptions and product flow diagram

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Describe the steps in PRINCE2 planning
  • Explain the purpose of the project product description
  • Describe the product breakdown structure, product descriptions and product flow diagram

It's time to plan the York shop the PRINCE2 way, starting with the products, not the tasks.

Let's say the first draft of Sam's plan lists 120 activities. Then Priya asks, "Where's the menu board?" It's not there. No activity mentioned it, so nobody planned it.

How do you make sure nothing is missed?

Select the arrow to learn more

1 of 4

Start with the end product

Describe the final product: an open, working York shop. Then ask what it's made of.

The planning steps

PRINCE2 7th edition planning follows these steps:

  • Define and analyse the products
  • Organise the work packages
  • Prepare estimates
  • Prepare the schedule
  • Prepare the budget, including any risk budget, change budget and tolerances
  • Analyse the risks in the plan
  • Document the plan

The project product description

The first product to describe is the final one. The project product description describes what the project must deliver to be accepted. It's created in starting up a project.

For York, it covers the purpose of the shop, its main parts, the customer's quality expectations, the acceptance criteria (like "chiller holds 1–5°C" and "counter height 95cm") and who accepts it.

Breaking down the products

Three techniques help define the products:

  • Product breakdown structure: a hierarchy of every product the project needs, from the final product down to its parts
  • Product descriptions: a description for each significant product, covering its purpose, composition, quality specifications and who checks it
  • Product flow diagram: shows the order in which products are created and how they depend on each other

From products to a plan

Once the products are clear, Sam groups them into work packages for each team. Then come the estimates, the schedule and the budget.

The York budget comes out at £85,000: £77,000 across the three stages, a £5,000 risk budget and a £3,000 change budget. Then Sam analyses the plan's risks and writes it up for the board.

Key points to remember

  • PRINCE2 plans start by defining and analysing products, then the activities.
  • The project product description describes the final product and its acceptance criteria.
  • A product breakdown structure, product descriptions and product flow diagram define the products.
  • The budget includes stage costs plus any risk budget and change budget.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

In which process is the project product description created?

In which process is the project product description created?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.