Tolerances
How the seven performance targets are given tolerances at each level, and where those tolerances are recorded.
Scene 1
Tolerances
How the seven performance targets are given tolerances at each level, and where those tolerances are recorded.
Caption 1 of 3
Name the seven performance targets that can have tolerances
Read all scene text
- Name the seven performance targets that can have tolerances
- Describe who sets tolerances at each level
- Identify where each tolerance is documented
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Name the seven performance targets that can have tolerances
- Describe who sets tolerances at each level
- Identify where each tolerance is documented
It's time to set the limits that let everyone get on with their work.
Let's say Stage 2 is planned at £40,000 and the first invoices suggest it'll come in at £40,800. Sam wonders whether to call an emergency board meeting. You'd rather not be called for £800.
When should Sam call you?
Select the arrow to learn more
1 of 4
Agree a range
When you authorised Stage 2, you set it at £40,000 ±£3,000 and 10 weeks ±1 week.
The seven performance targets
In PRINCE2 7th edition, tolerances can be set for seven performance targets:
- Benefits: the benefits the project should enable
- Cost: the money to be spent
- Time: the dates by which things should be done
- Quality: how good the products need to be
- Scope: what will and won't be delivered
- Risk: how much risk is acceptable
- Sustainability: the agreed environmental, social and economic targets
Who sets tolerances
Tolerances cascade down the levels of organisation:
- The business layer sets project tolerances
- The project board sets stage tolerances, within the project tolerances
- The project manager sets work package tolerances, within the stage tolerances
Where tolerances are documented
Each tolerance is written down in the most relevant place:
- Time, cost and scope: in the project plan, stage plans and work packages
- Quality: in the project product description and product descriptions
- Benefits: in the business case, and in stage plans
- Risk and sustainability: in the business case at project level, and in stage plans and work packages below that
Tolerances and management by exception
Tolerances are what make management by exception work. Each level gets on with the job without asking permission, as long as the forecast stays within its limits.
That saves a lot of time. You don't hear about the £800, but you do hear about the £5,000 damp, as soon as it's forecast, not after the money is spent.
Key points to remember
- Tolerances are the permissible deviation from a plan's targets.
- They can be set for benefits, cost, time, quality, scope, risk and sustainability.
- Business layer, board and project manager set tolerances at project, stage and work package level.
- Forecasting a breach of tolerance triggers escalation to the level above.
Knowledge check
Choose one answer
Practices
Where is quality tolerance for the final product documented?
Sign in to save your result. Knowledge checks can be retried any time.