Managing a stage boundary

How the project manager prepares the board to decide whether to continue, at the end of each stage or after an exception.

Sign in to track progress
Guided lesson
~0:24Scene 1 of 7
123

Scene 1

Managing a stage boundary

How the project manager prepares the board to decide whether to continue, at the end of each stage or after an exception.

Caption 1 of 3

Describe the purpose of managing a stage boundary

0:00 / 0:24
Read all scene text
  1. Describe the purpose of managing a stage boundary
  2. Name the main activities and outputs
  3. Explain how exception plans use this process

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Describe the purpose of managing a stage boundary
  • Name the main activities and outputs
  • Explain how exception plans use this process

It's time to reach the end of Stage 2.

Let's say the building works finished in week 11, a week late and at £44,500 under the approved exception plan. Before Kit's team starts the fit-out, the board needs to decide whether York is still worth it.

What does the board need to know?

Select the arrow to learn more

1 of 4

How did Stage 2 go?

Sam's end stage report covers what was delivered, the actual cost and time, the issues and risks, and the lessons learned.

Purpose

The purpose of managing a stage boundary is to give the board enough information to review the current stage, approve the next stage plan, review the updated project plan and confirm the project is still justified.

It happens near the end of every stage except the last, and also when an exception plan is needed.

Main activities

Managing a stage boundary includes:

  • Plan the next stage, or produce an exception plan if requested
  • Update the project plan
  • Update the business case
  • Report stage end, with an end stage report and any lessons

Exception plans

When the board asks for an exception plan, the project manager uses managing a stage boundary to prepare it, even though the stage isn't over.

That's what happened in week 5, when the damp pushed Stage 2 out of tolerance. Sam prepared the Stage 2 exception plan, updated the business case and project plan, and the board approved it.

Lessons at the boundary

The end stage report should include lessons. Stage 2 taught you to survey old buildings for damp before signing contracts.

If a lesson is useful for the wider business, a lessons report passes it on. Tom could use the damp lesson when looking at a third shop.

Key points to remember

  • Managing a stage boundary prepares the board to decide whether to continue.
  • It happens near the end of every stage except the last, and for exception plans.
  • It updates the project plan and business case and plans the next stage.
  • It produces the end stage report, including lessons.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Processes

Which report summarises how a stage performed?

Which report summarises how a stage performed?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.