What is an issue?

The five types of issue in PRINCE2 7th edition and how each one should be handled.

Sign in to track progress
Guided lesson
~0:20Scene 1 of 7

Scene 1

What is an issue?

The five types of issue in PRINCE2 7th edition and how each one should be handled.

Caption 1 of 3

Define an issue in PRINCE2 terms

0:00 / 0:20
Read all scene text
  1. Define an issue in PRINCE2 terms
  2. Name the five types of issue
  3. Decide whether to handle an issue formally or informally

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Define an issue in PRINCE2 terms
  • Name the five types of issue
  • Decide whether to handle an issue formally or informally

It's time to deal with the things that actually happen.

Let's say it's week 5 on York. On Monday the survey confirms damp. On Tuesday Priya asks for a bigger oven. On Wednesday the council announces road works outside the shop in November. By Thursday, Sam's inbox is full.

Are these all the same kind of thing?

Select the arrow to learn more

1 of 4

A problem

The damp is a problem that's now happening. It needs fixing, and it affects cost and time.

The five types of issue

PRINCE2 7th edition describes five types of issue:

  • Request for change: a proposal to change a baseline, like Priya's bigger oven
  • Off-specification: something that should be provided, but isn't, or isn't going to be, like a counter built 5cm too low
  • Problem or concern: anything else the project manager needs to resolve or escalate, like the damp
  • Business opportunity: a chance to deliver more benefit, like a local café asking to buy your bread wholesale
  • External event: something outside the project that affects it, like the road works

Risk or issue?

Remember the difference: a risk might happen; an issue has happened. When the survey confirmed damp, the damp risk became an issue.

One event can also create new risks. The road works are an issue now, but they create a risk that opening-week sales fall short.

Formal or informal

Not every issue needs paperwork. If the project manager can deal with it within tolerance and without a change to a baseline, it can be handled informally and noted in the daily log.

When Kit says a delivery of tiles will arrive a day late, with no effect on the stage plan, Sam just notes it. The damp, which threatens Stage 2's tolerance, needs formal handling in the issue register.

Anyone can raise an issue

Anyone with an interest in the project can raise an issue: board members, team members, suppliers, even neighbours. Jo might notice that customers can't see the menu from the queue.

The project manager makes sure every issue is captured and handled consistently, using the issue management approach.

Key points to remember

  • An issue is an unplanned event that has happened and needs management attention.
  • The five types are request for change, off-specification, problem or concern, business opportunity and external event.
  • Issues the project manager can handle within tolerance can be managed informally in the daily log.
  • Formal issues are recorded in the issue register.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

Priya asks to replace the agreed oven with a bigger model. What type of issue is this?

Priya asks to replace the agreed oven with a bigger model. What type of issue is this?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.