Module 5Session 31 of 6614 minKnowledge check

Commercial and communication approaches

How the project plans its relationships with suppliers and how it will keep every stakeholder informed.

Sign in to track progress
Guided lesson
~0:24Scene 1 of 7

Scene 1

Commercial and communication approaches

How the project plans its relationships with suppliers and how it will keep every stakeholder informed.

Caption 1 of 3

Explain the purpose of the commercial management approach

0:00 / 0:24
Read all scene text
  1. Explain the purpose of the commercial management approach
  2. Explain the purpose of the communication management approach
  3. Recognise how customer and supplier interests are aligned through contracts

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Explain the purpose of the commercial management approach
  • Explain the purpose of the communication management approach
  • Recognise how customer and supplier interests are aligned through contracts

It's time to plan how the project deals with suppliers and stakeholders.

Let's say Mistry Build's quote says "building works: £40,000". In week 5, Dev sends a bill for £1,200 of extra skips. "Waste removal wasn't included," Dev says. You thought it was.

How could this have been avoided?

Select the arrow to learn more

1 of 4

Unclear terms

Nobody wrote down what the £40,000 included, how extras would be priced or who approved them. Both of you assumed something different.

The commercial management approach

PRINCE2 7th edition includes a commercial management approach, prepared during initiation. It explains how products will be bought in and how supplier relationships will be managed. It usually covers:

  • Sourcing: which products are made in-house and which are bought
  • Selection: how suppliers are chosen, for example by quote or tender
  • Contracts: the type of contract, what's included and how payments work
  • Managing suppliers: how performance is monitored and changes are agreed
  • Responsibilities: who can sign contracts and approve extra costs

Two sides, two business cases

In a customer–supplier project, each side has its own reasons. Fern & Flour wants a great shop for £85,000. Mistry Build wants to make a profit and keep a good client.

A good contract aligns these interests. For the app, you might pay Pixel & Pine per 2-week cycle, so both sides can review progress regularly and either can stop if it isn't working.

The communication management approach

You met communication in the People module. In the organising practice, the communication management approach turns that into a plan. It's prepared during initiation and typically sets out:

  • Stakeholders and their information needs
  • Methods and frequency: board meetings, highlight reports, site notices, newsletters
  • Responsibilities: who communicates with whom
  • Feedback: how stakeholders can raise concerns and ideas

Reviewing the approaches

Both approaches are reviewed at each stage boundary. The cast changes as the project moves on. In Stage 3, Oakline becomes the main supplier, and York staff and new customers become key stakeholders.

Keep both proportionate. For York, each approach might be a page or two. For a large multi-supplier project, they'd be far more detailed.

Key points to remember

  • The commercial management approach plans sourcing, contracts and supplier management.
  • Customer and supplier each have their own business reasons; contracts should align them.
  • The communication management approach plans how stakeholders are engaged.
  • Both approaches are prepared during initiation and reviewed at each stage boundary.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

When is the communication management approach prepared?

When is the communication management approach prepared?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.