Starting up a project

The pre-project process that checks the idea is worthwhile and prepares the ground for initiation.

Sign in to track progress
Guided lesson
~0:24Scene 1 of 7

Scene 1

Starting up a project

The pre-project process that checks the idea is worthwhile and prepares the ground for initiation.

Caption 1 of 3

Describe the purpose of starting up a project

0:00 / 0:24
Read all scene text
  1. Describe the purpose of starting up a project
  2. Name the main activities and outputs of starting up
  3. Explain the role of the project mandate and project brief

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Describe the purpose of starting up a project
  • Name the main activities and outputs of starting up
  • Explain the role of the project mandate and project brief

It's time to go back to the very beginning of York.

Let's say you and Tom have just agreed, over a cup of tea, that York should be next. Tom writes a one-page note: "Open a second shop in York by December. Budget around £85,000." That's the trigger.

What happens next?

Select the arrow to learn more

1 of 4

The mandate

Tom's note is the project mandate: the trigger from the business layer that says a project might be needed.

Purpose

The purpose of starting up a project is to answer one question: do we have a viable and worthwhile project? It stops poorly thought-out projects starting and gives good ones a solid foundation.

It's triggered by the project mandate, which can be anything from a formal document to Tom's one-page note.

Main activities

The main activities in starting up are:

  • Appoint the executive and the project manager
  • Capture previous lessons, recorded in the lessons log
  • Design and appoint the project management team
  • Prepare the outline business case
  • Select the project approach and assemble the project brief
  • Plan the initiation stage

Main outputs

Starting up produces:

  • The project brief, including the outline business case, the project product description and the project approach
  • The initiation stage plan
  • The daily log and lessons log
  • The appointed project management team and their role descriptions

What it leads to

Starting up ends with a request to the board to authorise initiation. That's the first decision in directing a project.

If the board agrees, the project officially begins and moves into the initiation stage. If not, it stops, having spent very little.

Key points to remember

  • Starting up is triggered by the project mandate from the business layer.
  • Its purpose is to check the project is viable and worthwhile.
  • It appoints the executive, project manager and team, and captures previous lessons.
  • It produces the project brief and the initiation stage plan.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Processes

Which product contains the outline business case and project product description?

Which product contains the outline business case and project product description?
Choose one answer to continue.