The project board
The three roles on the project board, what each is responsible for and what makes a board effective.
Scene 1
The project board
The three roles on the project board, what each is responsible for and what makes a board effective.
Caption 1 of 3
Describe the roles of project executive, senior user and senior supplier
Read all scene text
- Describe the roles of project executive, senior user and senior supplier
- Explain why there is only one project executive
- Recognise the qualities of an effective project board
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Describe the roles of project executive, senior user and senior supplier
- Explain why there is only one project executive
- Recognise the qualities of an effective project board
It's time to set up the York project board.
Let's say Tom suggests, "Why don't we both be the executive? Then we share the decisions." It sounds fair. You're equal partners in the business, after all.
Should you and Tom share the executive role?
Select the arrow to learn more
1 of 4
Picture a tough call
The damp pushes Stage 2 over tolerance. You want to carry on; Tom wants to pause. With two executives, who decides?
The project executive
The project executive represents the business interest and is ultimately accountable for the project. That's you.
- Owns the business case and secures the funding
- Chairs the board and makes the final decision when views differ
- Makes sure the project stays aligned with the business's goals
- Appoints, or approves, the project manager and the rest of the project management team
Senior user and senior supplier
The senior user represents the people who'll use the products. Priya specifies what the users need, makes sure the products meet those needs and is accountable for showing that the user benefits are realised.
The senior supplier represents the people who'll design and build the products. Dev Mistry commits supplier resources, makes sure the work is technically sound and is accountable for the quality of what the suppliers deliver.
More than one user or supplier
Unlike the executive, the senior user and senior supplier roles can be shared by more than one person. If Oakline's work is a big part of the project, Kit's managing director could join Dev as a second senior supplier.
Keep the board small, though. A board of eight people won't make quick decisions. Each member should be able to speak for their area and commit resources.
What makes a good board
An effective project board has members who have:
- Authority to make decisions and commit resources
- Credibility within their part of the project
- The ability to delegate, leaving day-to-day management to the project manager
- Availability to make decisions when they're needed
Key points to remember
- The project board is made up of the project executive, senior user(s) and senior supplier(s).
- There is only one project executive, who is ultimately accountable.
- The senior user represents users; the senior supplier represents suppliers.
- Good board members have authority, credibility, availability and the ability to delegate.
Knowledge check
Choose one answer
Practices
Who is accountable for the quality of the products delivered by suppliers?
Sign in to save your result. Knowledge checks can be retried any time.