Module 8Session 42 of 6613 minKnowledge check

Threats and opportunities

What a risk is in PRINCE2, why it can be positive or negative, and how to describe one clearly.

Sign in to track progress
Guided lesson
~0:20Scene 1 of 7

Scene 1

Threats and opportunities

What a risk is in PRINCE2, why it can be positive or negative, and how to describe one clearly.

Caption 1 of 3

Define a risk in PRINCE2 terms

0:00 / 0:20
Read all scene text
  1. Define a risk in PRINCE2 terms
  2. Distinguish threats from opportunities
  3. Describe a risk using cause, event and effect

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Define a risk in PRINCE2 terms
  • Distinguish threats from opportunities
  • Describe a risk using cause, event and effect

It's time to think about what might happen, before it does.

Let's say Dev mentions, during the first site visit, that the back wall "looks a bit damp". Nothing's wrong yet. The plaster's fine. But if there is damp, fixing it could cost thousands and add weeks.

Is this a problem yet?

Select the arrow to learn more

1 of 4

Not yet

Nothing has gone wrong. It's something that might happen. That makes it a risk, not an issue.

Risks vs issues

A risk is something that might happen. An issue is something that has happened, or is happening, and needs management attention.

If the damp survey confirms damp, the risk has become an issue. You'll learn how to handle issues in the next module.

Cause, event, effect

Describing a risk clearly makes it easier to manage. A useful format splits it into three parts:

  • Cause: the situation that gives rise to the risk. "The building is over 100 years old and the back wall shows signs of moisture..."
  • Event: the uncertain thing that might happen. "...there may be rising damp needing treatment..."
  • Effect: the impact on the objectives. "...which would add up to £5,000 and two weeks to Stage 2."

Opportunities count too

PRINCE2 7th edition treats opportunities as seriously as threats. A project that only manages threats misses chances to deliver more.

Other York opportunities: a supplier offering a discount for early payment, or a local food festival in November that could launch the shop.

Risk appetite and tolerance

Risk appetite is how much risk the business is willing to take. Risk tolerance sets the limits on that, beyond which risks must be escalated.

Fern & Flour is a small business, so your risk appetite is fairly low. A risk that could delay opening past Christmas, your busiest time, would need to be escalated to the board straight away.

Key points to remember

  • A risk is an uncertain event that would affect objectives if it happened.
  • Threats have negative effects; opportunities have positive ones.
  • Describe risks by cause, event and effect.
  • Risk appetite and tolerance set how much risk the business accepts.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

What is the difference between a risk and an issue?

What is the difference between a risk and an issue?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.