Module 11Session 58 of 6613 minKnowledge check

Directing a project

How the project board makes its key decisions, from authorising initiation to authorising closure.

Sign in to track progress
Guided lesson
~0:18Scene 1 of 7

Scene 1

Directing a project

How the project board makes its key decisions, from authorising initiation to authorising closure.

Caption 1 of 3

Describe the purpose of directing a project

0:00 / 0:18
Read all scene text
  1. Describe the purpose of directing a project
  2. Name the board's key decisions
  3. Explain how the board gives ad hoc direction

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Describe the purpose of directing a project
  • Name the board's key decisions
  • Explain how the board gives ad hoc direction

It's time to look at the project from the board's side of the table.

Let's say you're worried about being stuck in meetings all year. You run a bakery. Sam reassures you: "You won't need to manage anything. You'll make a few big decisions, and I'll come to you if something goes outside the limits."

What exactly will the board decide?

Select the arrow to learn more

1 of 4

Start planning?

After starting up, you decide whether to authorise initiation: is the idea worth planning properly?

Purpose

The purpose of directing a project is to let the board be accountable for the project's success by making key decisions and keeping overall control, while delegating day-to-day management to the project manager.

It starts after starting up a project and runs until the project closes.

The key decisions

Directing a project has five activities:

  • Authorise initiation: approve the project brief and initiation stage plan
  • Authorise the project: approve the PID and the project plan
  • Authorise a stage or exception plan: approve the next stage plan, or an exception plan
  • Give ad hoc direction: respond to reports, issues and requests whenever needed
  • Authorise project closure: confirm the project can close

Ad hoc direction

Between the big decisions, the board stays informed through highlight reports and gives direction when it's needed. That might be answering a question, resolving an issue or responding to an exception report.

When the coffee chain announced its opening, you asked Sam to review the York sales forecast. That's ad hoc direction.

Linking to the business layer

The board also keeps the business layer informed. You and Tom talk about York regularly, and anything beyond the project's tolerances goes to the business layer to decide.

When the project closes, the board makes sure responsibility for any remaining benefit reviews passes to the business layer.

Key points to remember

  • Directing a project lets the board stay accountable through key decisions.
  • It runs from the end of starting up until the project closes.
  • The board authorises initiation, the project, each stage or exception plan, and closure.
  • It gives ad hoc direction whenever needed between decisions.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Processes

When does directing a project begin?

When does directing a project begin?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.

PRINCE2® is a registered trademark of the PeopleCert group. MockAcademy is independent and not affiliated with, endorsed by or licensed by PeopleCert.