Controls and escalation

The controls each level uses to monitor and direct the project, and what happens when tolerance is threatened.

Sign in to track progress
Guided lesson
~0:22Scene 1 of 7
123

Scene 1

Controls and escalation

The controls each level uses to monitor and direct the project, and what happens when tolerance is threatened.

Caption 1 of 3

Distinguish event-driven from time-driven controls

0:00 / 0:22
Read all scene text
  1. Distinguish event-driven from time-driven controls
  2. Describe the controls used by the board and the project manager
  3. Describe how exceptions are escalated

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Distinguish event-driven from time-driven controls
  • Describe the controls used by the board and the project manager
  • Describe how exceptions are escalated

It's time to handle the damp exception step by step.

Let's say the survey confirms damp in week 5. Treatment will cost £5,000 and add a week. Stage 2's forecast is now £45,000, which is £2,000 beyond its tolerance.

What happens next?

Select the arrow to learn more

1 of 4

Sam raises an exception

Sam sends you an exception report: what's happened, the options and a recommendation. Sam can't approve the extra money alone.

Event-driven and time-driven controls

PRINCE2 7th edition uses two kinds of control:

  • Event-driven: triggered when something happens, such as the end of a stage or a forecast exception. Examples: end stage report, exception report, issue report
  • Time-driven: happen at regular intervals. Examples: highlight reports and checkpoint reports

Board controls

The project board controls the project through:

  • Authorisations: of initiation, of the project, of each stage and of closure
  • Progress updates: highlight reports, end stage reports and the end project report
  • Exceptions and changes: exception reports, issue reports and requests for change

Project manager controls

The project manager controls the stage through:

  • Authorising work packages to team managers
  • Checkpoint reports from team managers
  • Logs and registers, like the issue and risk registers, to track what's happening

Escalating at project level

If the whole project is forecast to go outside its tolerances, the board can't decide alone. It escalates to the business layer.

If the damp had pushed York beyond its £85,000 budget tolerance, you'd have taken it to the business layer, as a director with Tom. The business layer might approve a project exception plan, or close the project.

Key points to remember

  • Controls are either event-driven or time-driven.
  • The board controls through authorisations, progress updates and exceptions.
  • The project manager controls through work packages, checkpoint reports and logs and registers.
  • Forecast tolerance breaches are escalated to the level above.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

Stage 2 is forecast to exceed its cost tolerance. What does Sam send the board?

Stage 2 is forecast to exceed its cost tolerance. What does Sam send the board?
Choose one answer to continue.