The seven performance targets
The seven things every PRINCE2 project is measured against, how they pull against each other, and how they lead to tolerances.
Scene 1
The seven performance targets
The seven things every PRINCE2 project is measured against, how they pull against each other, and how they lead to tolerances.
Caption 1 of 3
Name the seven performance targets
Read all scene text
- Name the seven performance targets
- Explain why the targets have to be balanced against each other
- Describe how a target becomes a tolerance
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Name the seven performance targets
- Explain why the targets have to be balanced against each other
- Describe how a target becomes a tolerance
It's time to look at how you'll know whether the project is going well.
Let's say your accountant sits you down a week before the builders start. "You're about to spend most of your savings," they say. "How will we know if the York project is on track?"
What would you measure?
Select the arrow to learn more
1 of 5
Money and the calendar
Are we spending what we planned, £85,000? And will we open by 1 December? That's cost and time.
The seven performance targets
Every PRINCE2 project sets targets in the same seven areas. Here's what they look like for the York shop:
- Benefits: York must add £4,000 of sales a week within a year of opening
- Cost: the fit-out budget is £85,000
- Time: the shop must open by 1 December, before the Christmas rush
- Quality: the kitchen must achieve a top food hygiene rating at its first inspection
- Scope: what's included (kitchen, counter, seating for 20) and what isn't (no delivery van)
- Risk: how much uncertainty you're willing to accept, for example no single threat that could cost more than £10,000
- Sustainability: all-electric ovens, and at least 90% of packaging recyclable
Targets pull against each other
The targets are connected. Change one and the others move.
If you want to open two weeks earlier, the builder may need to bring in a second team, so cost goes up. If Priya, your head baker, wants a bigger oven, scope grows and so may time. If you switch to cheaper packaging to save money, you may miss your sustainability target.
That's why decisions on a project are trade-offs. Part of managing a project is making those trade-offs openly, with the right people involved, rather than letting them happen by accident.
From targets to tolerances
A target on its own is a single number, and real projects rarely hit numbers exactly. So PRINCE2 lets you set a tolerance around each target: an allowed range above or below it.
For example, cost might be "£85,000, plus or minus £4,000". As long as the forecast stays inside that range, Sam, your project manager, gets on with the job without asking you. If it's forecast to go outside, Sam must tell you straight away.
Key points to remember
- Every project is measured against seven performance targets: benefits, cost, time, quality, scope, risk and sustainability.
- Sustainability was added as a performance target in the 7th edition.
- The targets are connected, so project decisions are trade-offs.
- A tolerance is an allowed range around a target, so people can act without constant approval.
Knowledge check
Select all that apply
Foundations
Which of these are PRINCE2 performance targets? Select all that apply.
Sign in to save your result. Knowledge checks can be retried any time.