Distinguish a project from business as usual
Read all scene text
- Distinguish a project from business as usual
- Name and recognise the five characteristics of a project
- Explain the key words in how PRINCE2 describes a project
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Distinguish a project from business as usual
- Name and recognise the five characteristics of a project
- Explain the key words in how PRINCE2 describes a project
It's time to work out what is, and isn't, a project.
Let's say it's Monday morning at the Leeds shop. You have three things on your list: order this week's flour, set up the rota for the new Saturday assistant, and get the York shop open by 1 December.
Which of these is a project?
Select the arrow to learn more
1 of 4
Ordering flour
You do it every week, the same way, with the same supplier. It's routine. This is business as usual.
Business as usual
Business as usual is the ongoing work that keeps an organisation running: baking, serving, cleaning, ordering, paying staff. It's repeatable, and it's managed by the people who run the business day to day.
Projects exist to change business as usual. Once the York shop opens, running it becomes part of business as usual too. Part of every project's job is to hand over what it delivers so the business can use it.
The five characteristics of a project
So how do you spot a project? Look for five tell-tale characteristics. Here's how each one shows up in the York shop:
- Change: it creates something new for the business, a second shop and a new way of trading
- Temporary: the project team disbands once the shop opens and is handed over
- Cross-functional: builders, bakers, a shopfitter and your accountant must work together, each bringing different skills
- Unique: you've never opened in York before, so even with experience, this one is different
- Uncertainty: damp walls, late deliveries and price rises can all happen, and you can't know for sure in advance
How PRINCE2 describes a project
PRINCE2 has a precise way of describing a project. Rather than memorise a sentence, learn the three key words it's built on:
- Temporary organisation: a project is a team of people brought together for a limited time, with its own roles and decision-making, then disbanded
- Products: the project exists to deliver one or more things the business needs, such as the fitted shop, the trained staff and the opening-day stock
- Business case: there must be an agreed reason that makes it worth doing, and that reason is checked throughout
Outputs, outcomes and benefits
Projects deliver products, but nobody wants a shop for its own sake. PRINCE2 separates three ideas you'll meet again in the business case practice:
- Output: what the project produces. The fitted York shop.
- Outcome: the change that results from using it. Customers in York buying your bread every day.
- Benefit: the measurable improvement that makes it worthwhile. An extra £4,000 of sales a week.
Key points to remember
- Business as usual is ongoing and repeatable. Projects change it.
- Projects show five characteristics: change, temporary, cross-functional, unique and uncertainty.
- PRINCE2 describes a project using three key ideas: a temporary organisation, products and a business case.
- Outputs are what you build, outcomes are what changes, and benefits are what you gain.
Knowledge check
Select all that apply
Foundations
Which of these are characteristics of a project? Select all that apply.
Sign in to save your result. Knowledge checks can be retried any time.