Quality planning and quality control
The two halves of the quality practice: agreeing what quality means up front, then checking products against it.
Scene 1
Quality planning and quality control
The two halves of the quality practice: agreeing what quality means up front, then checking products against it.
Caption 1 of 3
Explain what quality means in PRINCE2
Read all scene text
- Explain what quality means in PRINCE2
- Distinguish quality planning from quality control
- Explain the difference between quality assurance and project assurance
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Explain what quality means in PRINCE2
- Distinguish quality planning from quality control
- Explain the difference between quality assurance and project assurance
It's time to make sure the York shop is good enough. But good enough for whom, and how will you know?
Let's say the chiller cabinet arrives and Oakline says it's finished. Priya opens it and says it isn't cold enough. Kit says it's "within the normal range". Nobody ever agreed what the right temperature was.
Who's right?
Select the arrow to learn more
1 of 4
No agreed standard
Without a written standard, it's Priya's opinion against Kit's. The argument could go on for weeks.
What quality means
In PRINCE2, quality is about whether a product is fit for purpose: it meets the requirements and expectations agreed for it.
That's not the same as "the best possible". A marble counter would be higher grade than a laminate one, but if laminate meets the agreed needs, it's the right quality.
Quality planning
Quality planning happens early, mostly in starting up and initiation. It covers:
- Understanding the customer's quality expectations
- Turning them into measurable acceptance criteria
- Writing product descriptions with quality specifications for each product
- Agreeing the quality management approach
Quality control
Quality control happens during delivery. Each product is checked against its quality specifications using the agreed methods, and the results are recorded.
When a product passes, it's approved and can be handed over. When it fails, it's fixed and checked again, or the issue is escalated if it can't be fixed within tolerance.
Quality assurance vs project assurance
Quality assurance checks that the project is following the organisation's quality standards and policies. It's done for the wider business, independently of the project management team.
Project assurance, as you saw in Organising, is done for the project board. Both are independent of the project manager, but they serve different audiences.
Key points to remember
- Quality means a product is fit for purpose and meets agreed requirements.
- Quality planning agrees what quality means and how it'll be checked.
- Quality control checks products against their quality specifications.
- Quality assurance serves the wider business; project assurance serves the board.
Knowledge check
Choose one answer
Practices
What does quality mean in PRINCE2?
Sign in to save your result. Knowledge checks can be retried any time.