Skip to content
0 / 66 sessions

Course contents

Module 8 of 13 · 66 sessions

PRINCE2® Foundation

Free
Course overview

Course progress

0%

0 of 66 sessions complete

Sign in to save your progress across devices.

Module 8Session 46 of 6612 minKnowledge check

Communicating risk and risk roles

Who owns and acts on each risk, and how risk information is shared with the board and stakeholders.

Sign in to track progress
Guided lesson
~0:22Scene 1 of 7

Scene 1

Communicating risk and risk roles

Who owns and acts on each risk, and how risk information is shared with the board and stakeholders.

Caption 1 of 3

Distinguish the risk owner from the risk actionee

0:00 / 0:22
Read all scene text
  1. Distinguish the risk owner from the risk actionee
  2. Describe how risks are communicated
  3. Explain who is responsible for risk at each level

Scenes animate with GSAP. Use pause or replay at any time.

In this session

  • Distinguish the risk owner from the risk actionee
  • Describe how risks are communicated
  • Explain who is responsible for risk at each level

It's time to make sure every York risk has someone looking after it.

Let's say the damp survey is agreed at the board, but three weeks later it hasn't happened. Sam thought Dev was booking it. Dev thought Sam was. Nobody was clearly in charge of it.

How do you stop this happening?

Select the arrow to learn more

1 of 4

Name an owner

Dev becomes the risk owner for the damp. Dev is responsible for managing and monitoring the risk and its responses.

Risk owner and risk actionee

The risk owner is responsible for managing a particular risk: monitoring it and making sure the responses are carried out. They should be the person best placed to keep an eye on it.

A risk actionee carries out a specific response, on behalf of the owner. One risk might have several actionees for different actions.

Who does what

Risk responsibilities by role:

  • Business layer: sets the risk appetite and project risk tolerance
  • Project executive: is accountable for all aspects of risk management on the project
  • Senior user and senior supplier: own risks that relate to their interests
  • Project manager: creates the risk management approach and register and manages risk day to day
  • Team managers: help identify and manage risks in their work packages
  • Project support: helps maintain the risk register

Communicating risk

Risk information is shared through the project's normal reports:

  • Checkpoint reports: team managers tell the project manager about risks in their work
  • Highlight reports: the project manager updates the board on key risks
  • End stage reports: summarise the risks at the end of each stage
  • Exception reports: explain risks behind a forecast tolerance breach

Keep it alive

A risk register written in initiation and never looked at again is no use. Risks change. New ones appear; old ones close or turn into issues.

When the coffee chain announces it's opening two doors down, that's a new threat to your sales forecast. It goes straight into the register and up to the board.

Key points to remember

  • The risk owner manages and monitors a risk.
  • The risk actionee carries out specific risk responses.
  • The project executive is accountable for risk management on the project.
  • Risk information is shared through checkpoint, highlight, end stage and exception reports.
Knowledge checkQuestion 1 of 4

Knowledge check

Choose one answer

Practices

Who sets the risk appetite for the project?

Who sets the risk appetite for the project?
Choose one answer to continue.

Sign in to save your result. Knowledge checks can be retried any time.

PRINCE2® is a registered trademark of the PeopleCert group. MockAcademy is independent and not affiliated with, endorsed by or licensed by PeopleCert.