Tailoring PRINCE2
What tailoring means, what can and can't be tailored, and who decides how PRINCE2 is applied.
Scene 1
Tailoring PRINCE2
What tailoring means, what can and can't be tailored, and who decides how PRINCE2 is applied.
Caption 1 of 3
Explain what tailoring means in PRINCE2 7th edition
Read all scene text
- Explain what tailoring means in PRINCE2 7th edition
- Identify which parts of PRINCE2 can be tailored
- Describe who is responsible for tailoring decisions
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Explain what tailoring means in PRINCE2 7th edition
- Identify which parts of PRINCE2 can be tailored
- Describe who is responsible for tailoring decisions
It's time to make PRINCE2 fit, rather than fitting your project to PRINCE2.
Let's say Tom wants to run a pop-up stall at the York Christmas market: one weekend, £1,500, three people. Sam starts drafting a full PID. Tom laughs. "It's a gazebo and some mince pies."
Does a tiny project need all of PRINCE2?
Select the arrow to learn more
1 of 4
Keep the principles
The stall still needs a reason (sell, and promote York), clear roles, a plan and some idea of what could go wrong. The principles all apply.
What can be tailored
Almost everything can be tailored, except the principles:
- Practices: how much detail is needed, using the organisation's own procedures
- Processes: combining or simplifying activities
- Roles: combining roles, within the rules you've learned
- Management products: merging, simplifying or using different formats
- Terminology: using the organisation's own words, as long as the meaning is clear
Why tailor
Applying PRINCE2 the same way to every project causes problems. Too much process on a small project wastes time and annoys people. Too little on a big one leaves it out of control.
Tailoring also helps PRINCE2 work alongside other methods, such as an agile approach on the app, or a supplier's own building standards.
Who tailors
The project manager proposes how the method will be tailored. The project board approves it, and project assurance checks it's appropriate.
The business layer may have its own standards that limit or guide tailoring. A large company might insist on a standard risk register template, for example.
Recording tailoring
Tailoring decisions are agreed in initiation and recorded in the PID. They're reviewed at each stage boundary, because what suits one stage may not suit the next.
For York, the PID notes that highlight reports are a one-page email every two weeks, the board can decide by phone and the quality register is a spreadsheet tab.
Key points to remember
- Tailoring adapts PRINCE2 to the project's context.
- Practices, processes, roles, products and terminology can be tailored; principles can't.
- The project manager proposes tailoring and the board approves it.
- Tailoring decisions are recorded in the PID and reviewed at stage boundaries.
Knowledge check
Choose one answer
Project context
Where are tailoring decisions recorded?
Sign in to save your result. Knowledge checks can be retried any time.