Project manager and team manager
What the project manager and team managers are responsible for, and how work is passed between them.
Scene 1
Project manager and team manager
What the project manager and team managers are responsible for, and how work is passed between them.
Caption 1 of 3
Describe the responsibilities of the project manager
Read all scene text
- Describe the responsibilities of the project manager
- Describe the responsibilities of a team manager
- Explain how work packages connect the two roles
Scenes animate with GSAP. Use pause or replay at any time.
In this session
- Describe the responsibilities of the project manager
- Describe the responsibilities of a team manager
- Explain how work packages connect the two roles
It's time to look at the people who run the project day to day.
Let's say Sam is on site every morning, checking the plaster, chasing deliveries and telling the crew where to put the shelves. The site foreman is getting irritated, and Sam is too busy to update the plan or talk to the landlord.
What's going wrong?
Select the arrow to learn more
1 of 4
Two jobs, one person
Sam is trying to manage the project and supervise the building crew. The foreman's job is being done twice, and Sam's own job isn't being done at all.
The project manager
The project manager runs the project day to day on behalf of the board, within the tolerances the board sets. There's only one project manager, and the role isn't shared.
- Plans each stage and monitors progress
- Authorises work packages and agrees them with team managers
- Manages risks, issues and changes, escalating when tolerances are at risk
- Reports to the board and keeps stakeholders informed
- Leads the project team and keeps everyone focused on the plan
The team manager
A team manager makes sure the products in a work package are built on time, to budget and to the right quality. They lead their team and report progress to the project manager.
On York, the site foreman manages the building works and Kit manages the fit-out. On the pre-order app, Ana is the team manager for the development team.
Work packages and checkpoint reports
Work passes from the project manager to a team manager in a work package. It describes the products to deliver, the tolerances, how quality will be checked and how often to report.
The team manager reports back with checkpoint reports at the agreed frequency. If the work is forecast to go outside its tolerances, the team manager raises it with the project manager straight away.
Combining roles
Some roles can be combined, but not all. The project manager and project executive roles can't be combined, because the executive needs to hold the project manager to account. That's one reason you don't manage York yourself.
The project manager can, however, take on the team manager role or project support on a small project. What matters is that every responsibility is clearly covered.
Key points to remember
- The project manager runs the project day to day within the board's tolerances.
- Team managers make sure their products are built on time, to budget and to quality.
- Work packages pass work down; checkpoint reports pass progress back up.
- The project executive and project manager roles can't be combined.
Knowledge check
True or false
Practices
The team manager role is optional on a PRINCE2 project.